Level 4 Commissioning and Testing Equipment



On December 1, 2017, the National Energy Administration made corresponding adjustments to the qualification equipment for electric power commissioning and testing. The qualification equipment for commissioning and testing is the same in each province and region, while some equipment that is not commonly used in the actual work of electric power enterprises was omitted. Obtaining the Level 4 commissioning and testing qualification allows for the installation, maintenance, or testing of electric power facilities with voltage levels below 35 kV.

Level 4 commissioning and testing equipment includes series resonance, power frequency withstand voltage test devices, DC high voltage generators, induced withstand voltage test devices, dielectric loss testers, loop resistance testers, and transformation ratio testers.

Article 17: Those who obtain the Level 4 commissioning and testing qualification for electric power facility installation (repair, testing) can engage in testing activities for electric power facilities with voltage levels below 35 kV. Applicants shall meet the following conditions:

(1) Legal person qualification and a complete organizational structure;

(2) Net assets of more than 6 million yuan;

(3) The technical director and safety director shall have more than 3 years of experience in the management of electric power facility testing, and shall have junior or above technical qualifications in electric power-related majors;

(4) More than 10 professional technical and economic management personnel, including more than 4 electric power-related professional engineering and technical personnel;

(5) More than 6 electricians with grid access operation permits, including more than 2 high-voltage electricians and more than 3 special electricians;

(6) A sound and effective safety production organization and system, carrying out safety training in accordance with the law, with more than 1 safety management personnel;

(7) A fixed business site with a total area of more than 400 square meters, various professional laboratories, and testing equipment for electric power facilities with voltage levels above 35 kV;

(8) A sound technical file management system. [2]